Hi,
I came to know that every Job defined in CA7 may not be a scheduled Job, if it is not a scheduled Job how can I check that when a particular job will get executed?
Thanks for your help.
Display the calendar for jobs not scheduled in CA-7.
-
- New Member
- Posts: 5
- Joined: Wed Apr 23, 2014 12:30 pm
- Robert Sample
- Global Moderator
- Posts: 1896
- Joined: Fri Jun 28, 2013 1:22 am
- Location: Dubuque Iowa
Re: Display the calendar for jobs not scheduled in CA-7.
Jobs can be triggered via date / time in CA-7, but they can also be triggered by the completion (or failure) of another job, or even by the creation of a data set on the system. In the latter two cases, there is no schedule for them since CA-7 doesn't consider them to be calendar-based.
-
- New Member
- Posts: 5
- Joined: Wed Apr 23, 2014 12:30 pm
Re: Display the calendar for jobs not scheduled in CA-7.
Thanks Robert. Then for such job how can I see their scheduling pattern?
- Robert Sample
- Global Moderator
- Posts: 1896
- Joined: Fri Jun 28, 2013 1:22 am
- Location: Dubuque Iowa
Re: Display the calendar for jobs not scheduled in CA-7.
I don't know of a general way (but then I am not a CA-7 expert). If you list the individual job, you can see how it is triggered.
Create an account or sign in to join the discussion
You need to be a member in order to post a reply
Create an account
Not a member? register to join our community
Members can start their own topics & subscribe to topics
It’s free and only takes a minute